Prepare an approximate estimate of building project with totalplinth area of all building is 800 sqm. and from following data. i) Plinth area rate Rs. 4500 per sqm ii) Cost of water supply @7� %of cost of building. iii) Cost of Sanitary andElectrical installations each @ 7�% of cost ofbuilding. iv)Cost of architectural features @1% of building cost. v)Cost of roads and lawns @5% of building cost. vi) Cost of P.S. and contingencies @4% of building cost. Determine the total cost of building project.

 Prepare an approximate estimate of building project with totalplinth area of all building is 800 sqm. and from following data.

 

i) Plinth area rate Rs. 4500 per sqm

 

ii) Cost of water supply @7� %of cost of building.

 

iii)  Cost of Sanitary andElectrical installations each @ 7�%  of cost ofbuilding.

 

iv)Cost of architectural features @1% of building cost.

 

v)Cost of roads and lawns @5% of building cost.

 

vi)    Cost  of  P.S.  and  contingencies  @4%  of  building

 

cost. Determine the total cost of building project.

 

Solution:

 

Data given:

 

Plinth area = 800m2

 

Plinth area rate = Rs. 4500 per Sq.m

 

Cost of building = 800 x 4500 = Rs. 36,00,000=00

 