Monday, October 10, 2022

The top width of an embankment is 2 m. Side slopes on both the sides are 2:1. Level of the top surface of this bank is at 250 m. NSL at 30m interval are given below. Calculate earth work by Mean Area Metho

 

Q#:The top width of an embankment is 2 m. Side slopes on both the sides are 2:1. Level of the top surface of this bank is at 250 m. NSL at 30m interval are given below. Calculate earth work by Mean Area Method.

 

Station

0

30

60

90

120

150

N.S.L

248.15

248.50

249.25

248.75

248.15

247.75

 

Solution#

 

 

Station no.

Depth

Bd

Sd²

A(m²)

Mean area (m²)

interval

Q(m³)

 

1.65

3.7

6.845

10.545

--

--

 

 

1.5

3

4.5

7.5

9.02

30

270.6

 

0.75

1.5

1.125

2.655

5.06

30

151.8

 

1.25

2.5

3.125

5.125

4.125

30

123.75

 

1.65

3.7

6.845

10.545

8.08

30

242.4

 

2.25

4.5

10.125

14.625

12.585

30

377.55

 

 

 

 

 

 

 

 

Find out the quantity of STIRRUPS in kg for 8 feet length of beam, Cross section of the beam is given in Figure 2. Assume missing data if any.

 

Q#: Find out the quantity of STIRRUPS in kg for 8 feet length of beam, Cross section of the beam is given in Figure 2. Assume missing data if any.

 

Solution#

Lenghth of beam  =   8 beams

        = 8-0.125 -0.125 = 7.75

 

NO.of stirrups =  7.7/ 0.5 +1 =16.5 = 17

 

Length of 1  stirrup  =  2×L +2×B  + 2 × (10 d)                              d= 0.375 of #3bars

 

= 2 (12 -0.125 -0.125 ) + 2(18 -0.125 -0.125) + 9(0.375) +9(0.375) -6(0.375) -6(0.375)

 

=50.25 =  4.1875ft

 

Total legth of stirrups = 4.1875 × 17 = 71.1875

 

 

Total weight of stirrups = 71.1875  × 0.1701  = 12.1089 kg

Find out the quantity of steel in Kg for the given slab. (Figure 1). Assume missing data

 

Q#: Find out the quantity of steel in Kg for the given slab. (Figure 1). Assume missing data.

Solution#

Solution

 No. of Bars horizantally

 

19×12= 228''  => 228/7  = 32.57  = 33bars

 

Lengtht 20'    => total = 660 feet  #3 steel

 

No. of Bars vertically;

 

20×12 = 240  => 240/5 = 48+1  = 49 bars

 

 At lngth 21’     => total = 1029 feet

 

 5’×5’ deduction 6''/7 and 6''/5  =>  9bars and 12bars

 

5’×5’ total deduction 105ft => so 660  +1029 – 105  = 1584 feet

 

#1feet weight in kg = 0.171 kg => 0.171 × 1584 =  270.86 kg

 

=270.86 kg

 

Make an example that how government of Kp can use BOT type contract. Explain

 

Question; Make an example that how government of Kp can use BOT type contract. Explain

 Solution

 BOT Definition

              Under a build-operate-transfer (BOT) contract, an entity—usually a government—grants a concession to a private company to finance, build and operate a project. ... BOT projects are normally large-scale, greenfield infrastructure projects that would otherwise be financed, built and operated solely by the government

BOT  definition;       First published after having received the assent of the Governor of  thKhyber Pakhtunkhwa in the Gazette of Khyber Pakhtunkhwa (Extraordinary),dated the 7th April,2014].

AN ACT

To proviide for the participation of the private sector in the financing, construction, development, operation, or maintenance of infrastructure or development Projects or other related services of the Government through Concession Contracts in Public Private Partnership mode and the establishment of institutions to regulate, monitor and supervise the implementation of Public Private Partnership contracts.

Whereas is expedient to establish a favorable legislative framework to promote and facilitate the implementation of privately financed infrastructure Projects in form of Public Private Partnership by enhancing transparency, fairness and long-term sustainability and removing undesirable restrictions on private sector participation in shape of partnership with public sector in infrastructure development and operation

 Example of kpk BOT project The Government of Khyber Pakhtunkhwa and Frontier Works Organization (FWO) have agreed to jointly initiate the mega projects of the province in communication and energy production sectors under Public Private Partnership (PPP) policy of the present provincial government.

This was agreed upon at a meeting of the Director General FWO, Major General, Muhammad Afzal with Chief Minister KPK Khattak at CM Secretariat Thursday. Other relevant officers of FWO and the Communication and Works and Relief and Rehabilitation departments were also present.

The CM welcomed the offer made by FWO for executing the major infrastructure and energy projects and said that partnership between KP government and FWO will not only help improve quality of construction works but such venture would also ensure completion of the projects in much lesser time and at reduced cost.

He told FWO that the provincial government will give top priority to the proposed Swat Motorway and hydro power projects and his government was ready to award execution contract of these projects to FWO. He added that feasibilities of these projects have been completed by the government and they were available for consideration of FWO and other investors informing that certain foreign investors had also shown their keen interest in the projects. He also asked FWO to consider reconstruction of Peshawar Bus Terminal on modern lines.

It was decided during the meeting that a separate agreement between KP government and FWO would be finalized soon for handing over the rehabilitation and ADP schemes to FWO in the flood and earthquake-hit district of Chitral. However these schemes will be initiated after the current snowy season ends.

Khattak on this occasion assured to extend cooperation of the provincial government for permanent rehabilitation of Mirkhani-Arandu road in Chitral which will help boost tourism and mineral sectors besides providing better transport facilities to the commuters. Appreciating FWO’s offer for contributing in the “Billion Tree Tsunami” project, Mr. Khattak directed the environment department for providing saplings to FWO for plantation according to its demand.

The DG, FWO on this occasion expressed interest of his organization in execution of the provincial government’s development projects on BOT or PPP(public private partnershaip) basis and told that FWO was also successfully engaged in uplift projects of the Punjab and Sindh provinces. He also consented to the construction of Nishterabad, Peshawar flats.

Prepare a Tender Notice for the Construction of Government School at your Village. Assume all the data.

 

Prepare a Tender Notice for the Construction of Government School at your Village. Assume all the data.

Solution#1

Tender are invited for the construction of govt primery school at kohat,

Local government engineering deptt(LGED) invites tender for primary school No.3 kohat

It’s a govt school which provides quality education to young sampling of childern with professional teachers in creative path to enhance the knowledge.

 

Govt invites tender for construction of school with playing facilities at village from eligible certified contractor having experience in school construction ,

Tender No.

Name of work

 

SDR145PR763

Construction of govt school at village

Rs. 1200000

 

 

 

 

 

Tender proposal/security amount Rs,. 1200000

Tender proposal documents amount Rs,. 400

Start date : 19sep 2020

Completion date : 17july 2021

Tender proposal opening date : 5sept 2020

For further detail about tender and budget all are given in documents